BIS Documents After Renovating a Locally Protected Façade

What you need to file in Latvia’s Construction Information System (BIS) depends on the process used, the scope of work and the heritage permit. Use this checklist to identify what applies to the project.

Fasades.lv · A practical guide for building owners and property managers

1. Notify completion of the works

Use the document required by the construction case: Part II of the explanatory statement for work approved under that process, or a statement that the building or part of it is ready for use when a building permit was used. Check transitional rules for older cases. See paragraphs 157 and 167 of the Building Regulations.

Building Regulations

2. Prepare the construction records

Where applicable, prepare the following records in BIS and obtain approval from the responsible parties:

  • Entries in the construction log.
  • Acceptance records for the relevant completed works.
  • Declarations and other applicable evidence of conformity for the installed materials.
  • Testing and inspection reports where tests or inspections are required.
  • Construction supervision and design supervision records where those services were provided.
  • Construction waste records and evidence of transfer to the recipient, where applicable.

The BIS and State Construction Control Bureau (BVKB) guidance explain which records are used and how to maintain them electronically.

BIS construction log guidance · BVKB guidance

3. Close out the heritage works

Where a report on work to the protected monument is required, include:

  • A brief history of the building.
  • A description of its condition before and after the works.
  • A record of the work process and photographs.
  • Details of significant elements removed and how they are stored.
  • Corrections to the working drawings.

See paragraph 52 of Cabinet Regulation No. 720. Obtain an opinion confirming compliance with the heritage works permit if the permit or acceptance conditions require one. For a locally protected monument, contact the responsible municipal authority. In Riga, this service is provided by the City Development Department. Attach the report and opinion to BIS if required to close the case. Check submission to the heritage authority and attachment to BIS as separate steps.

Cabinet Regulation No. 720 · Riga heritage guidance

4. Check additional attachments

  • Design revisions or as-built drawings, where permissible changes were made.
  • The construction supervisor’s report on delivery of the supervision plan, where supervision was provided in the building-permit process.
  • Photographs of the façade as required by the applicable procedure.
  • Utility and authority opinions where their networks or requirements are affected.
  • Test reports and acceptance records for any installed equipment or systems, where applicable.
  • A provisional energy performance certificate or its BIS data, where required.
  • An as-built survey plan where the regulations require one.
  • Cadastral survey documentation where applicable, subject to the exceptions for unified registration.

See paragraphs 157, 163 and 167 of Latvia’s Building Regulations. Renewal of the façade finish alone does not mean every attachment on this list is required.

Building Regulations

Before submitting

Review the Required Opinions section of the BIS case, the works permit conditions and the status of each approval. BIS can identify required opinions based on the issuer’s conditions. Uploading a record does not approve it. Before submitting, confirm that all parties required by the procedure have approved the applicable documents. This article reflects the information checked on 31 October 2026. Confirm the final list against the conditions of the individual BIS case.

BIS guidance on required opinions