Ventilated Façade Installation

The installation method varies with the façade system and the type of cladding panels. A ventilated façade is built in layers so air can circulate naturally through the cavity between the insulation and the outer cladding. The airflow helps carry away excess moisture. Together with the insulation and cladding, the cavity can contribute to summer comfort and winter thermal performance. This is why the system is sometimes described as a breathing façade.

Ventilated façade installation and systems

The subframe supports the façade cladding and maintains the cavity between the outer finish and the insulation. Depending on the system, rails are made from aluminium, galvanised steel or stainless steel. Brackets and anchors connect the subframe to the supporting wall. The façade designer or subframe system supplier calculates the bracket layout and quantities for the project.

Important. Select the subframe to suit the cladding material, panel weight and dimensions, and the way the panels are attached or supported.

Ventilējamā fasāde

A ventilated façade includes insulation, a wind barrier, a loadbearing subframe, a ventilated cavity and cladding panels.

What is a ventilated façade?

A ventilated façade is a widely used type of external cladding suitable for many modern buildings. The ventilated cavity sits behind the outer cladding. The finish can improve the building’s appearance and help protect the wall assembly against precipitation and mechanical damage, subject to the properties of the selected system.

Types of ventilated façade subframes

Vertical subframe
Double subframe
Ventilējamās fasādes montāžas instrukcija un shēma
Ventilējamās fasādes karkasa montāža un izbūve

A vertical subframe is widely used because it is usually less expensive and simpler to install. Depending on the system, it can support ceramic cladding, metal cassettes, fibre cement boards and other panels. Clinker tiles, natural stone and terracotta panels secured with a kerf or similar edge fixing may need a different support arrangement. The system must be designed to resist the applicable compression and tension loads.

A double subframe usually costs more and takes longer to install. Combining horizontal and vertical rails allows loads to be distributed between the two directions and can provide additional capacity when designed for the project. The arrangement is suitable for a wide range of panel finishes, subject to the approved system and fixing detail.

Subframe materials

Galvanised steel subframe

Typically the lower-cost option. The Latvian comparison gives an indicative service life of around 50 years in a mildly corrosive atmosphere. Actual durability depends on the coating, exposure and maintenance.

Steel’s strength can accommodate heavier finishes and larger wall offsets, subject to design and verification. Some systems use a simpler load-bearing bracket arrangement. Steel is less thermally conductive than aluminium, although thermal bridging depends on the complete bracket and wall detail. Assess performance at elevated temperatures for the approved façade assembly.

Aluminium subframe

Indicative material cost starts at €22/m². The Latvian comparison gives an indicative service life of over 70 years in a mildly corrosive atmosphere. Actual durability depends on the alloy, finish, exposure and maintenance.

Aluminium is around one-third the density of steel, which can help where the supporting structure has limited capacity. It expands more than steel. Fixed and sliding connections and suitable panel joints accommodate thermal movement. The Latvian example compares 8–10 mm joints on an aluminium subframe with 4–5 mm on a steel subframe. Actual joint dimensions must follow the project and cladding system specification.

The design must account for permitted panel weights, the strength of the selected alloy and performance at elevated temperatures. Fire performance is assessed for the complete specified or tested façade assembly.

Stainless steel subframe

Typically the highest-cost option. The Latvian comparison gives an indicative service life of over 70 years in a mildly corrosive atmosphere. Select a grade appropriate to the exposure.

Stainless steel’s corrosion resistance makes it an option for coastal and industrial sites. Check the grade and system for the required strength, fire and thermal performance.

Ventilated façade installation step by step

Typical installation sequence

  1. Survey the wall, mark the bracket positions and install the brackets.
  2. Fit the insulation.
  3. Install the rails, such as L, hat or omega profiles.
  4. Finish window reveals and fit sills.
  5. Install the selected cladding.
Ventilējamās fasādes attēls Rīgā
This example uses a double subframe and metal cassettes for the outer finish.

Metal or aluminium cassettes are commonly used on offices, commercial and industrial buildings. Installation can be among the costlier cladding options. Cassettes are available in different colours and shapes, with visible or concealed fixings.

Visible fixings. Joints and fasteners remain visible. In the system described here, the fixings can be finished in the façade colour so they are less noticeable.

Concealed fixings. The fasteners and connections sit behind the face of the cladding, giving the façade a more continuous appearance. In this example, work proceeds from the bottom upwards, and the top of each cassette is fixed to the rail with self-drilling screws. A concealed fixing system typically costs more.

1. Install the support brackets

Shēma kā ventilējamai fasādei uzstādīt karkasu un leņķus

1. Measure and mark the bracket positions on the wall, check the level and drill using a tool and bit suitable for the substrate. Use a percussion drill where appropriate for the wall material and the anchor manufacturer’s instructions.

Ventilējamās fasādes izlīmeņošana ar līmeņrādi
Fasādes uzmērīšanas darbi

2. Install the support brackets. Use the specified thermal isolation pads between the brackets and the wall to reduce thermal bridging. Select anchors designed for the wall material and the calculated loads. Stainless steel anchors may be suitable where specified for strength and corrosion resistance. Fit the subframe rails to the brackets after the insulation is in place.

Leņķu montāžas shēma ventilējamā fasāde
Leņķu stiprināšana uz fasādes

2. Fit the stone wool insulation

Fasādes siltināšana un ventilējamā fasāde

1. Use a suitable insulation knife or saw to cut slots in the stone wool. Fit the boards over the support brackets so the brackets pass through the cut-outs.

Ventilējamas fasādes leņķu montāža fasādei
Akmens vates līmēšana fasādei

2. Secure the insulation with fixings suited to the substrate and the insulation thickness. Use the quantity and fixing pattern specified for the assembly. The example uses an average of five to six fixings per square metre.

Akmens vates griešana, lai veiktu fasādes siltināšanu
Akmens vates dībelēšanas darbi fasādes siltināšanas laikā
Ventilējamās fasādes siltināšanas darbi ar akmens vati uz kronšteiniem
Ventilējamās fasādes siltināšana

3. Install the wind barrier membrane

Ventilējamās fasādes siltināšana un pretvēja plēve

The wind barrier membrane protects the insulation from wind and moisture. Secure it with façade fixings in accordance with the system. Overlap the membrane joints and seal them with compatible joint tape.

4. Assemble the ventilated façade subframe

Ventilejamas fasades dubuta tērauda vai alum;inija karkasa uzstādīšana
  1. 1. Attach the L-shaped rails to the brackets with the specified rivets or screws. Check the level of the rails and align the subframe to a consistent plane as you work.
tiek skūrvēts ventilējamās fasādes karkass
Profilu montāža ventilejamai fasādei
Ventilejamas fasādes karkasa montāža un uzstādīšana
HAT profilu uzstādīšana fasādei

2. Pre-drill where required and fit the hat profiles with suitable rivets.

Kakrkasa montāžas darbi ventilejamai fasādei
Fasādes karkasa stiptināšana ar kniedēm
Ventilējamās fasādes karkass
Fasādes karkasa montāžas shēma

The cavity between the cladding and insulation allows air to circulate and helps remove moisture. The example uses a cavity of 20–50 mm. Follow the design and system specification for the chosen assembly.

5. Install the metal cassette cladding

Ventilējamās fasādes mezgls, kas ietver sevī siltināšanu, karkasu un ventilējamās fasādes loksnes
  1. Fit the base profile and cushioning tape.
cokola profila montāžas darbi ventilejamai fasādei
Tiek montēts karkass ventilejamai fasadei

2. Start installing the metal or aluminium cassettes at a lower corner and work upwards. Fit the corner cassettes first, and use a spirit level to check horizontal and vertical alignment during installation.

Ventilējamās fasādes loksnu montāža
Ventilejamas fasades montāža

Installing the cassettes completes the sequence shown here. The photograph shows the intended finish when the specified installation method has been followed.

ventilējamās fasādes alumīnija kompozīta paneļi