To apply for Riga’s 2027 co-funding programme for the renovation of residential façades and roof coverings, prepare the full project file. In addition to the application and the contractor’s quotation, include the owners’ authorisation, a building condition report, approved construction documentation and a signed construction contract.
Fasades.lv · A practical guide for building owners and property managers
Completed street façade of a multi-storey building in Riga.
Sections IV and V of the competition rules list the required documents.
Use Appendix 1 of the competition rules. If the technical documents are available in Latvia’s Construction Information System (BIS), give the relevant construction case number in the application. See paragraph 38.1.
The documents depend on the form of ownership:
The authority must cover implementing the project, settling payments with the contractor, representing the applicant in the competition, signing the co-funding agreement and amendments, and receiving funds into the authorised person’s account. See paragraph 38.2 and the templates in Appendices 7, 8 and 9.
On 12 February 2027, the technical condition report must be no more than two years old. It must address:
State when an element is absent. The summary must meet the competition rules on safety in use, mechanical resistance and stability. If defects are identified, review the exceptions and requirements for correcting them. See paragraphs 27–30 and 38.4.
Provide evidence that the proposed works have been approved by the Riga City Development Department, along with the applicable endorsement or decision confirming that the conditions for starting works are satisfied. A colour scheme passport alone is insufficient. The rules allow the commencement endorsement to follow later in limited circumstances, provided the request for it was submitted at least five working days before the application deadline. See paragraphs 25–26, 38.5 and 44.2.8.
Where the rules require it, attach the works permit from the National Heritage Board or the municipality. A National Heritage Board permit must approve the relevant construction documentation and remain valid through the final project activity. If a reply is pending, provide proof of the submission date in the circumstances allowed by the rules. See paragraphs 38.6 and 44.2.9.
Use Appendix 2 and identify eligible costs separately. A certified civil engineer prepares the estimate, the construction contractor agrees it, and both the works contractor and the co-funding recipient sign it. Submit the signed estimate and the spreadsheet with its formulas intact. The rules specify .xls, while the official template is published as .xlsx. Confirm the accepted format with the organiser before submitting. Break down scaffolding costs separately where applicable. VAT, overheads and profit are ineligible. See paragraphs 16 and 38.7–38.7.2.
Provide the design solutions and drawings, explanatory statement or design description, and a construction organisation plan or works layout appropriate to the project. Copies are unnecessary if the documents are already in BIS and the application identifies the BIS case number. See paragraph 38.8.
Use Appendix 3. The works contractor and co-funding recipient sign the programme. Its works and dates must match the estimate and construction contract. Include submission of the documents needed to receive co-funding as the final activity. The latest date for that activity is 15 November 2027. See paragraphs 14, 32 and 38.9.
Attach the signed construction contract, the estimate and the programme. The documents must clearly set out the scope, amounts and deadlines. The contract must be consistent with the estimate and programme submitted for the competition. See paragraphs 32 and 38.10.
Attach a colour print of a photograph of the property and mark the façade, roof or relevant section to be renovated on the image. The photograph must demonstrate that the area meets the requirement for visibility from public space. See paragraphs 6 and 38.11.
Check whether the project also requires:
Paper submission deadline: 12 February 2027 at 09:00. Even when the remaining records are submitted electronically, the paper package must include:
Bind the paper documents as one volume and submit them in a sealed envelope. Deliver them in person at Kalēju iela 10, Riga, or by courier to Riharda Vāgnera iela 5, Riga, LV–1050. Courier deliveries must arrive by the deadline.
Send electronic documents to atjauno@riga.lv with a secure electronic signature and timestamp by 17:00 on the preceding working day. Identify the competition, property address and cadastral designation. Attach the estimate spreadsheet with its formulas intact. See paragraphs 39–41.
A complete, compliant project submitted by 09:00 on 2 February 2027 may earn five additional points, provided the earlier electronic submission requirement is also met. See paragraphs 42 and 44.4.5. Use the official programme page for the current forms, rules and organiser contact details.
Contact us to discuss costs for your façade project.